A bathroom remodel price is built from the work in the order it happens:
- Protection and demolition: containment, floor protection, removing fixtures and finishes, and haul-off.
- Rough-in: framing changes, blocking, plumbing supply and drain, electrical circuits and the fan duct.
- Walls and waterproofing: drywall, cement board, waterproofing membrane and the shower pan.
- Tile: setting, grouting and caulking floors and walls.
- Fixtures and finish: tub or shower, vanity, toilet, faucets, trim, paint and the punch list.
Common line items and how each is measured
These are the common lines on a bathroom estimate. Each is measured one of three ways:
- By the square foot: area work.
- By the linear foot: drain runs.
- By the each: fixtures and whole tasks.
The hours and prices are yours to set. Your crew and your subs work at their own pace, and every line's hours are editable.
| Line item | Measured in |
|---|---|
| Bathroom gut demolition of fixtures and finishes | Each |
| Demo wall tile down to studs | Square feet |
| Rough-in shower valve and water supply | Each |
| Relocate dwv drain line | Linear feet |
| Rough-in gfci receptacle circuit | Each |
| Install exhaust fan and duct to exterior | Each |
| Hang moisture-resistant drywall | Square feet |
| Install cement board on shower walls | Square feet |
| Apply liquid waterproofing membrane | Square feet |
| Build mortar bed shower pan with liner | Each |
| Set ceramic wall tile | Square feet |
| Set porcelain floor tile | Square feet |
| Grout tile walls | Square feet |
| Set alcove bathtub | Each |
| Install vanity cabinet | Each |
| Set toilet | Each |
| Paint walls two coats semi-gloss | Square feet |
| Final punch list and fixture adjustment | Each |
Tile is where bathroom labor adds up
Example: Take a shower with 80 square feet of wall tile and a 40-square-foot floor. The hours below are example figures; say your own records show your crew needs:
Work Your hours Cement board on the walls 2.5 Waterproofing membrane 1.5 Wall tile 10 Floor tile 4.5 Grouting walls and floor 4.5 Total 23 That's before the shower pan, the trim pieces and the caulk.
Price each trade at its own rate
A bathroom isn't one trade, so it shouldn't have one labor rate. Plumbers, electricians and tile setters earn different wages, and those wages differ by metro.
BuildWell builds each line's rate in three steps:
- Wage: the median wage for that line's trade in your metro.
- Overhead: your labor overhead, which starts at 100%, doubling the wage.
- Markup: your labor markup, which starts at 20%.
Example: Say your tile setter costs you $30 an hour. Use your real number. Those 23 hours of tile work come to:
- Wages: 23 × $30 = $690
- With 100% overhead: $1,380
- With 20% markup: $1,656 for that labor
Subbed trades: your sub's price plus markup
If you sub out a trade, replace its lines with your sub's price plus your markup. The estimate still shows the client the work, and your total still covers your coordination.
Price materials at this week's local cost
Price the materials you buy at what they cost near the job this week, plus your markup. BuildWell starts material markup at 20%.
Use allowances for finishes the client picks
For finishes the client chooses, set an allowance: a dollar amount per square foot of tile, or per vanity and per faucet.
Say in your terms how selections are billed:
- Above the allowance: billed as a change.
- Below the allowance: credited.
Clients understand allowances. They protect you from a $4 tile becoming a $22 tile after the estimate is signed.
Price permits, lead work and hidden conditions
- Permits: most jurisdictions require one when plumbing or electrical work changes. Add your permit fee as its own line. In BuildWell, a flat permit fee is added automatically when the estimate includes permits.
- Homes built before 1978: the EPA's Renovation, Repair and Painting rule requires lead-safe work practices, done by a certified renovator, when you disturb painted surfaces. Price the setup, containment and cleanup as their own line.
- What's behind the wall: for subfloor, rot and hidden plumbing, state what's included and how you'll price what you find. The client agrees to the method before demolition, not after.
Bill a deposit, then progress payments
Bathroom remodels run for weeks and front-load material costs. A common structure:
- Deposit: at signing, to order materials.
- Progress payments: after rough-in passes inspection, and after tile.
- Balance: at completion.
Check your state's rules: some limit how much deposit a home improvement contractor can take.