BuildWell

Free Concrete Calculator

Pick a slab, footing or columns, enter the sizes, and get cubic yards and bags.

What you’re pouring

Results

Volume33.33 cu ft
Cubic yards1.23
Cubic yards to order (with extra)1.36
80 lb bags62

Materials only. BuildWell prices them at stores near the job.

How to use it

Steps to use the free concrete calculator

  1. 1

    Pick the shape

    A slab, patio or walk; a continuous footing; or round columns and piers poured in form tubes.

  2. 2

    Enter the sizes

    Lengths in feet, thickness, widths and diameters in inches. The calculator converts.

  3. 3

    Add extra and pick a bag

    Extra for spillage and an uneven base, and the bag size if you’re mixing it yourself.

How concrete is measured

Concrete is ordered by volume. Ready-mix trucks deliver it by the cubic yard, which is a cube 3 feet on each side, or 27 cubic feet. Bagged mix is sold by weight, and each bag yields a set volume once mixed, printed on the bag.

Volume is length × width × depth, with every measurement in feet. Most of the trouble comes from mixing units: slab thickness is given in inches, so a 4 inch slab is 4 ÷ 12 = 0.333 feet thick. The calculator converts for you.

Measure the forms, not the plan. Forms are rarely perfectly square, the subgrade is rarely perfectly flat, and a slab that’s 4 inches on the drawing can be 4½ inches in the low spots. That’s what the extra allowance is for.

The concrete formulas

Slab, patio or walk: length (ft) × width (ft) × thickness (in) ÷ 12 = cubic feet.

Continuous footing: length (ft) × width (in) ÷ 12 × depth (in) ÷ 12 = cubic feet.

Round columns or piers: π × (diameter (in) ÷ 24)² × height (ft) × how many = cubic feet. Dividing the diameter by 24 turns it into the radius in feet.

Then for every shape:

  • Cubic yards = cubic feet ÷ 27.
  • To order = cubic yards × (1 + extra).
  • Bags = cubic feet to order ÷ the bag’s yield, rounded up.

Typical yields printed on bagged concrete mix are about 0.6 cubic feet for an 80 lb bag, 0.45 for a 60 lb bag and 0.3 for a 40 lb bag.

Bags per cubic yard

BagTypical yieldBags per cubic yardBags per 10 cu ft
80 lb0.6 cu ft4516.7
60 lb0.45 cu ft6022.2
40 lb0.3 cu ft9033.3
Yields are typical of bagged concrete mix. Use the yield printed on your bag.

A yard of concrete is 45 bags of 80 lb mix. That’s 3,600 pounds of bags to unload, mix and place, which is why larger pours usually come on a truck.

Coverage by slab thickness

How far a yard goes at common thicknesses, and what 100 square feet takes.

ThicknessSq ft per cubic yardCubic yards per 100 sq ft80 lb bags per 100 sq ft
3 in1080.9342
3.5 in92.61.0849
4 in811.2356
5 in64.81.5470
6 in541.8584
8 in40.52.47112
No extra included. Add your allowance for spillage and an uneven base.

Columns, piers and form tubes

Volume per foot of height for round forms, and bags for a typical 4 foot pier.

DiameterCu ft per foot of height80 lb bags per foot80 lb bags for a 4 ft pier
6 in0.1960.332
8 in0.3490.583
10 in0.5450.914
12 in0.7851.316
14 in1.0691.788
16 in1.3962.3310
18 in1.7672.9512
24 in3.1425.2421
Volume = π × radius² × height. No extra included.

Doubling the diameter quadruples the volume. A 16 inch pier holds four times the concrete of an 8 inch one, foot for foot.

Worked examples

A 10 × 10 patio, 4 inches thick

10 × 10 × 4 ÷ 12 = 33.33 cubic feet, or 1.23 cubic yards. With 10% extra, 36.67 cubic feet, or 1.36 yards. In bags: 36.67 ÷ 0.6 = 61.1, so 62 bags of 80 lb mix. Or 82 bags of 60 lb, or 123 bags of 40 lb.

A 40 foot footing, 16 inches wide and 8 inches deep

40 × (16 ÷ 12) × (8 ÷ 12) = 35.56 cubic feet, or 1.32 cubic yards. With 10% extra, 1.45 yards, or 66 bags of 80 lb mix.

Six deck piers, 12 inches across and 4 feet deep

π × 0.5² × 4 = 3.14 cubic feet each, 18.85 for all six, or 0.70 cubic yards. With 10% extra, 20.73 cubic feet, so 35 bags of 80 lb mix.

How much extra to order

Five to ten percent is a common allowance. It covers:

  • An uneven subgrade. Low spots in the base become thick spots in the slab.
  • Form bulge. Forms flex a little under the weight of wet concrete.
  • Spillage and what stays in the mixer, the wheelbarrow and the chute.

Running short in the middle of a pour can leave a cold joint, where fresh concrete meets concrete that has started to set. It’s a weak spot and it shows. A little left over is cheaper.

Bags or ready-mix

For a few post holes or a small pad, bags are simple. As the job grows, the bags grow fast: one yard is 45 bags of 80 lb mix, and two yards is 90. Mixing that much by hand or in a small mixer takes a crew most of a day, and the first batches can start to set before the last ones are placed.

At around a yard or more, price a ready-mix delivery against the bags. Ask the supplier about minimum loads, short-load charges and how long the truck can wait. Ready-mix also lets you specify the strength and any additives the job needs.

Common mistakes

Mixing inches and feet. 10 × 10 × 4 is 400, not 33.33. Divide the thickness by 12 first.

Forgetting the base. A slab needs a compacted gravel base, and that’s its own material and its own labor.

No control joints. Concrete shrinks as it cures and cracks where it wants to. Joints tell it where. A common rule of thumb is joints spaced two to three times the slab thickness in inches, in feet: 8 to 12 feet apart in a 4 inch slab, cut about a quarter of the slab deep.

Skipping the cure. Concrete gains strength over weeks, not hours. Keeping it moist, or using a curing compound, makes a stronger surface.

Pouring in heat and wind without a plan. A hot, windy day dries the surface fast, and that can open shallow shrinkage cracks before the slab is even finished. Dampen the base, line up enough hands to finish, and start curing as soon as the finish is done.

Ordering exactly what the math says. The math is for perfect forms on a perfect base. Add the extra.

From quantities to an estimate

The concrete itself is only part of a flatwork job. The estimate also needs demolition and haul-out if there’s an old slab, excavation and grading, gravel base, forms, reinforcement, finishing, joints, curing and cleanup.

When you estimate concrete work in BuildWell, describe the job and it plans each of those as its own line with labor hours. Materials are priced at stores near the job, checked within 30 days, and labor at your metro’s wage plus your overhead and markup. You can change any quantity, hour or price before you send it.

BuildWell

Estimate the whole job, priced for your area

Describe the job and BuildWell plans the line items and labor hours, prices materials at stores near the job and labor at your area’s wage, and adds your overhead, markup and tax.

Weekly
$7.99 / week
Billed weekly. Cancel anytime.
  • AI estimates priced for your area
  • Estimates, invoices, clients and projects
  • Clients sign on any phone
  • Card and bank payments, no extra BuildWell fee
  • iPhone, Android and the web
Start free trial
Best value
Annual
$79.99 / year
About $6.67 a month, billed yearly
  • AI estimates priced for your area
  • Estimates, invoices, clients and projects
  • Clients sign on any phone
  • Card and bank payments, no extra BuildWell fee
  • iPhone, Android and the web
Start free trial

Both plans include every feature and start with a 3-day free trial. Add a card to start; you’re not charged until the trial ends. Cancel anytime.

Concrete calculator FAQ

01How many 80 lb bags of concrete are in a yard?
About 45. A typical 80 lb bag yields about 0.6 cubic feet, and a cubic yard is 27 cubic feet: 27 ÷ 0.6 = 45.
02How many 60 lb and 40 lb bags make a yard?
At the typical yields of 0.45 and 0.3 cubic feet, 60 bags of 60 lb or 90 bags of 40 lb. Check the yield printed on your bag.
03How thick should a concrete slab be?
Four inches is common for walks and patios, and five to six inches where vehicles drive. Your local code and the engineer’s drawings, if there are any, decide.
04How much extra concrete should I order?
Five to ten percent is a common allowance for spillage, an uneven base and form bulge. Running short in the middle of a pour is worse than a little left over.
05When should I order ready-mix instead of bags?
At a yard or two, mixing 45 to 90 bags by hand is a long day, and the pour can start to set before you finish. Compare the bags against a delivered load, including any short-load or delivery charges.
06How far apart should control joints be?
A common rule of thumb is two to three times the slab thickness in inches, in feet: 8 to 12 feet apart in a 4 inch slab, cut about a quarter of the slab deep.

Try BuildWell today

Estimates, invoices, e-signatures and payments in one place, on your phone and on the web.

Start for free →3-day free trial. Cancel anytime.