BuildWell

Retainage

Retainage is a portion of each progress payment that the client holds back until the work is complete, as security that the job gets finished.

Retainage, also called retention, is common on commercial and public projects and less so on residential remodeling. The contract sets the rate, often somewhere between 5% and 10% of each payment. On a $100,000 contract with 10% retainage, $10,000 sits with the owner until the end.

Retainage usually flows down. The owner holds it from the general contractor, and the general contractor holds it from subcontractors, often at the same rate. Some contracts reduce it once the job is half complete.

Release usually comes at substantial or final completion, after the punch list, closeout documents and final lien waivers are in. Getting all of that done quickly is how you get retainage back quickly.

Many states limit retainage, especially on public work, and set deadlines for releasing it. The rules differ by state and between public and private projects, so check your state’s prompt payment and retainage laws or ask a construction attorney.

On your invoices, show retainage as its own line: the amount earned, the amount held and the amount due now. Track total retainage per job as a receivable. It’s money you’ve earned, and it’s easy to forget once the crew has moved on.

How retainage works

Retainage is calculated on each progress payment, but it builds up across the job. On every pay request, the client works out the value of work completed to date, holds back the contract’s retainage rate on that value, and subtracts what it has already paid. The amount held grows with each billing until it’s released at the end.

The contract sets the rate and the release terms. Rates often fall between 5% and 10%. Retainage is usually calculated on work completed and on stored materials if those are billed. It can apply to the whole contract or be reduced once the work reaches a milestone, often half complete.

Retainage usually flows down the chain. The owner holds it from the general contractor, and the general contractor holds it from each sub, often at the same rate. A subcontract may say the sub’s retainage is released only when the general contractor gets its own retainage back, which can mean a sub that finished early waits until the whole job closes.

Release usually happens in one of two steps. Part or most of it may be released at substantial completion, with an amount kept to cover the punch list. The rest follows final completion, once the closeout package is in:

  • Punch list items finished and accepted.
  • Closeout documents delivered, such as warranties, manuals and as-built drawings.
  • Final lien waivers from the contractor and its subs and suppliers.
  • On bonded jobs, the surety’s written consent to final payment.

Retainage terms you’ll see in contracts

Contracts handle retainage in a few common ways, and the details change how much cash you wait for and for how long.

Common retainage arrangements
ArrangementHow it worksWhat to watch
Flat rateThe same rate is held on every billing until completionThe full amount waits until closeout
Reduced at a milestoneRetainage stops or drops once the work is, say, half completeWhether reduction is automatic or at the owner’s discretion
Early release by lineFinished trades get their retainage before the whole job closesWhether the subcontract passes that release down
Security instead of cashSome public contracts allow securities or a bond in place of cash retainageWhether the contract and your state allow it

Many states cap retainage on public work, and some cap it on private work too. Many also set deadlines for releasing it and, in some cases, interest on retainage paid late. The rules differ by state and between public and private projects, so check your state’s prompt payment and retainage laws.

Why retainage matters to each party

For contractors and subs

Retainage is earned money you can’t use yet. On a thin-margin job, the amount held can be larger than your whole profit, which means you may be financing the job until closeout. Price that wait into your bid, and treat closeout paperwork as part of the job, not an afterthought.

For owners and clients

Retainage gives the owner leverage to get the punch list finished and the closeout documents delivered. It is also a cushion if the contractor walks away or a sub files a lien. Holding more than the contract allows, or holding it long after completion, can break state prompt payment rules.

For general contractors

A general contractor is both holding retainage and waiting for it. Tracking what’s held from each sub against what the owner is holding avoids paying out retainage you haven’t received, or sitting on a sub’s retainage after the owner has released yours.

How to manage retainage step by step

  1. Before signing, read the retainage clause: the rate, any reduction point, release conditions and how it passes down to subs.
  2. Check your state’s retainage and prompt payment rules for the job type, public or private, and compare them with the contract.
  3. Show retainage on every invoice or pay application as its own line: work completed to date, retainage held and amount due now.
  4. Track retainage held per job as a receivable, with a running total.
  5. Request any reduction in writing as soon as the job reaches the milestone in the contract.
  6. Start the closeout package early: warranties, manuals, as-builts and waivers from your subs and suppliers.
  7. Request release in writing at substantial completion and again at final completion, and follow up on the dates the contract or state law sets.

The contractors who get retainage back fastest are usually the ones who treat closeout as a scheduled task with its own deadline. A finished job with missing paperwork can hold retainage for months.

Retainage example with numbers

Say a general contractor has a $240,000 tenant improvement contract with 10% retainage. For illustration, the contract says no further retainage is held on work done after the job is 50% complete. The contractor bills monthly on work completed to date.

Retainage on a $240,000 contract, reduced at 50% complete
BillingCompleted to dateRetainage heldPaid beforeThis payment
Month 1 (25%)$60,000$6,000$0$54,000
Month 2 (50%)$120,000$12,000$54,000$54,000
Month 3 (80%)$192,000$12,000$108,000$72,000
Month 4 (100%)$240,000$12,000$180,000$48,000
Retainage release$240,000$0$228,000$12,000

Each payment is completed to date, less retainage held, less what was paid before. In month 3, that is $192,000 − $12,000 − $108,000 = $72,000. Retainage stops growing at $12,000 because the contract stops holding it after 50% complete.

The five payments add up to $240,000: $54,000 + $54,000 + $72,000 + $48,000 + $12,000. Without the reduction, retainage would have reached $24,000, 10% of the full contract, all waiting on closeout.

The same terms usually flow down. If the general contractor has an $80,000 drywall subcontract with matching retainage terms, the most it can hold from that sub is 10% of the first $40,000 of work, or $4,000. If the sub finishes in month 3 but its retainage is only released when the owner releases the general contractor’s, the sub waits on everyone else’s closeout too.

Common retainage mistakes

  • Not pricing the cost of waiting for retainage into the bid on long jobs.
  • Leaving retainage off invoices, so the client’s records and yours disagree about what’s owed.
  • Forgetting to request a reduction the contract allows.
  • Signing a final lien waiver before retainage has actually been paid.
  • Letting closeout documents slide after the crew leaves, which delays release.
  • Accepting a subcontract that ties release to the whole project’s closeout without knowing how long that could take.
  • Writing off retainage that’s owed instead of following up in writing.

Retainage is easy to lose track of because it shows up months after the work. Keep a running list of every job with retainage outstanding and the date you can next ask for it.

Common questions

01How much retainage is typical?
The contract sets it, and rates often fall between 5% and 10% of each payment. Many states cap retainage on public projects, and some cap it on private ones, so check your state’s rules before you agree to a rate.
02When is retainage released?
Usually at substantial or final completion, after the punch list is done and closeout documents and final lien waivers are delivered. Some contracts release most of it at substantial completion and the rest at final. Many states set deadlines for releasing it, so check your state’s prompt payment laws.
03Can a homeowner hold retainage on a remodel?
If the contract provides for it, yes, though retainage is less common on residential remodeling than on commercial work. It has to be written into the contract with the rate and release terms. State rules may apply, so check with your state’s licensing board or a construction attorney.
04Does a general contractor have to pass retainage down to subs?
The subcontract sets the terms, and many states’ prompt payment laws require a general contractor to pay subs their share of retainage within a set time after receiving it. The details differ by state and by public or private work, so check your state’s rules.
05Is retainage the same as a holdback?
Mostly, yes. Retainage, retention and holdback are often used for the same thing: a share of each payment held until the job is done. Read the contract, though, since a holdback can also mean a specific amount kept for one unfinished item, such as a punch list.
06Is retainage held on change orders?
Usually, yes. Approved change orders are typically billed through the same pay applications, and retainage is held on them at the contract rate unless the contract says otherwise. Check the retainage clause, especially if the contract reduces retainage at a milestone.
BuildWell

Estimates, signatures and invoices in one app

BuildWell writes itemized estimates priced for your area, gets them signed on the client’s phone, and turns them into invoices.

Weekly
$7.99 / week
Billed weekly. Cancel anytime.
  • AI estimates priced for your area
  • Estimates, invoices, clients and projects
  • Clients sign on any phone
  • Card and bank payments, no extra BuildWell fee
  • iPhone, Android and the web
Start free trial
Best value
Annual
$79.99 / year
About $6.67 a month, billed yearly
  • AI estimates priced for your area
  • Estimates, invoices, clients and projects
  • Clients sign on any phone
  • Card and bank payments, no extra BuildWell fee
  • iPhone, Android and the web
Start free trial

Both plans include every feature and start with a 3-day free trial. Add a card to start; you’re not charged until the trial ends. Cancel anytime.

Try BuildWell today

Estimates, invoices, e-signatures and payments in one place, on your phone and on the web.

Start for free →3-day free trial. Cancel anytime.